Key innovation
Formalizes the allocation of scarce grid connection capacity and network-upgrade costs through queued interconnection studies instead of ad hoc connections.
Category
Energy
Abstraction level
Pojęcie
Operation level
Deployment
Use cases
Connecting data centers (AI infrastructure)Connecting solar and wind farmsConnecting battery energy storage (BESS)Connecting large industrial loadsTransmission grid expansion and upgrade planning

How it works

An applicant files an interconnection request and takes a position in the queue. The operator runs successive studies: feasibility, system impact and facilities studies, which determine the required network upgrades and their costs. On that basis an interconnection agreement (IA) is signed and capacity is reserved. In the serial "first-come, first-served" model projects are studied one at a time in order of submission, which creates backlogs when requests surge. Reforms (e.g. FERC Order 2023, and earlier PJM approved by FERC in November 2022) introduce cluster studies and a "first-ready, first-served" approach: projects are studied in groups and upgrade costs are shared across cluster members, aiming to shorten queues and screen out projects that are not ready.

Problem solved

Grid connection capacity is limited, and far more projects (renewables, storage, data centers) want to connect than the grid can accept without upgrades. The queue orders access, assigns the cost of required network upgrades and reserves capacity, preventing uncoordinated connections that would threaten system stability.

Components

Interconnection requestEntry point to the process and queue-position marker

A formal application to connect a project, which establishes a queue position and triggers the study process.

Interconnection studyAssessment of technical feasibility and connection costs

A series of analyses (feasibility, system impact, facilities) that determine the required network upgrades and their costs.

Capacity reservationGuarantee of available capacity for the connecting facility

Allocation and reservation of transmission/connection capacity for a project, typically after an interconnection agreement is signed.

Grid operator (TSO/DSO, ISO/RTO)Management of the queue and connection terms

The entity managing the transmission or distribution grid that runs the queue and studies and executes interconnection agreements.

Queue reform (cluster study)Mechanism to shorten queues and share upgrade costs

A shift from the serial "first-come, first-served" model to cluster studies and a "first-ready, first-served" approach (e.g. FERC Order 2023).

Evolution

2003
FERC Order 2003 — standardized interconnection procedures

Established pro-forma interconnection procedures (including NRIS and ERIS) under a "first-come, first-served" model.

2022
PJM — transition to "first-ready, first-served"

PJM, approved by FERC in November 2022, replaced its serial process with a clustered cycle that groups projects.

2023
FERC Order 2023 — overhaul of the interconnection process
Inflection point

Introduced mandatory cluster studies and a "first-ready, first-served" rule; published in the Federal Register in September 2023.

2024
LBNL "Queued Up: 2024" — ~2,600 GW in queues

At the end of 2023 about 2,600 GW (2.6 TW) of capacity was in US queues; the typical project waited nearly 5 years, and only ~20% of projects (2000-2018) reached commercial operation.