On 9 November 2026 Tmtpost published an analysis showing that European logistics warehouses have begun competing with data centres for the same thing — grid connection capacity. Automation raises a warehouse's electricity use roughly tenfold, and in the Netherlands 15,498 large entities are waiting for a new or expanded connection. In some regions the queue has passed ten years.
Key takeaways
- An automated warehouse consumes around ten times more electricity than a conventional one of the same size — a site that once needed 1 MVA may need 5–8 MVA once fully electrified
- By mid-2026, 15,498 large entities in the Netherlands were waiting for a new or expanded connection, and in the Diemen sub-grid the date for some 150 applications slipped from Q4 2036 to the end of 2037
- More than 44 percent of large warehouse users rank power supply as an important siting factor — twice the share of four years earlier
- Prologis directed $2.1B of its $3.9B in development starts over the first nine months of 2026 into data centre projects
- SEGRO's first fully fitted data centre in London's Park Royal has a 70 MVA connection — equivalent to the consumption of 7–14 large automated warehouses
Where does this start?
The Dutch clothing retailer Zeeman installed a new automated order-picking system at its distribution centre in Alphen. The installation works — except its electricity demand exceeded the upper limit of the existing grid connection.
In many congested areas of the Dutch grid, an application for new or expanded capacity means being placed on a waiting list. That queue has its own priorities: first projects that themselves relieve congestion, then safety functions — emergency medical services, police, fire and defence — and then basic needs, meaning housing, education and heating.
But a problem appears: an ordinary commercial warehouse falls into none of those categories, so it goes to the back of the queue.
And that is why warehouse operators started looking for solutions beside the grid rather than within it.
How did Zeeman get around the queue?
The solution has two parts, and neither requires expanding the connection.
The first is a capacity-limited contract. The distribution centre may draw higher capacity when the grid is not congested, and at moments when load must be curtailed the automated equipment switches to battery power.
The second part is the ownership model for that battery. The storage unit belongs to EcoPowerCell — Zeeman had to neither buy nor lease it. When the battery sits idle, the operator trades it on the energy market, and the revenue helps cover the financing cost of the whole system.
This is a simplified view of one deployment, described in the Tmtpost analysis, not a template for the whole sector.
Why does automation raise electricity use so much?
A traditional warehouse's consumption breaks down simply: lighting, ventilation, forklift charging. The new loads fall — per CBRE research from September 2026 cited in the analysis — into three categories: automated picking and sorting systems, charging infrastructure for delivery fleets, and temperature-controlled storage.
The scale of the difference is easy to show in numbers. A UK utilities consultancy gives rules of thumb per 10,000 square feet of floor area:
| Facility type | Capacity per 10,000 sq ft |
|---|---|
| Ordinary ambient-temperature warehouse | 5–15 kVA |
| Automated fulfilment centre | 50–150 kVA |
| Cold store | 100–300 kVA |
| Electric fleet depot | 100–500 kVA |
From that follows the jump a single site owner feels: the same floor area draws roughly ten times more after automation. A site that previously required 1 MVA may require 5–8 MVA once fully electrified.
Demand will keep rising. Per the analysis, 73 percent of tenants want their next warehouse to reach at least Level 2 automation. The larger variable is electric trucks: the ICCT together with the Fraunhofer Institute calculated that under a policy-friendly scenario European charging demand for such vehicles will reach about 100 TWh in 2035 and about 200 TWh in 2045, mostly at depots.
What do these names mean?
The analysis uses energy-sector units and terms that cannot be inferred from context.
- kVA and MVA — units of apparent power, meaning how much electricity a site may draw at peak. 1 MVA equals 1,000 kVA. This is the figure written into a connection agreement, not annual consumption.
- Grid connection queue — the list of entities waiting for a capacity allocation from the network operator. The equivalent of a queue for the only socket, with its own priority rules.
- Non-firm capacity contract — an agreement where supply is guaranteed only when the grid has headroom. Available in the Netherlands since January 2024 for large consumers in congested areas, in exchange for roughly a 50 percent discount on the connection fee.
- Peak shaving — keeping draw below contracted capacity by covering short spikes from a battery. It avoids penalties and avoids applying for a larger connection.
Together these four terms explain why a warehouse stops being a passive consumer of electricity. If more capacity cannot be obtained, the only route is managing one's own consumption profile over time.
Why not just expand the grid?
The simplest answer runs: if capacity is short, run more cable and build more substations.
The problem is time. Grid expansion takes a decade in practice, and logistics companies cannot wait that long. In the Diemen sub-grid, around 150 applications from Amsterdam customers were affected by a change to the construction schedule — the expected date for leaving the waiting list slipped from Q4 2036 to the end of 2037.
The second point is competition for the same connection points. Data centres need exactly what warehouses need: large industrial plots near a city and abundant power. In a Dutch-style queuing system, one data centre application for several dozen MVA takes the place of a whole group of warehouses.
The third problem sits on the building side. Under the revised Energy Performance of Buildings Directive, member states are to set thresholds based on 2020 energy use and bring the worst 16 percent of non-residential floor area into compliance by 2030, rising to 26 percent by 2033. The transposition deadline for the directive fell on 29 May 2026.
A contradiction worth noting arises here: automation, refrigeration and fleet charging all raise consumption per square metre, so the more modern a warehouse is, the greater the pressure on it in the energy-efficiency ranking may be.
Why do data centres win the power if they pay less per megawatt?
Intuition suggests data centres simply outbid warehouses. The arithmetic shows something else.
Per SEGRO's figures, a data centre yields about £330,000 of potential annual rent per MVA of capacity. On the warehouse side the sum runs as follows: Knight Frank reports that in Basildon near London prime warehouse rent reached £14.50 per square foot in the third quarter of 2026, which for a 500,000 square foot facility gives about £7.25M a year — at 5–10 MVA that is £730,000 to £1.45M per MVA.
In west London, where prime rates reach £29.50 per square foot, an automated warehouse can return roughly ten times as much per MVA as a data centre.
The data centre advantage therefore lies elsewhere: it can consume a great deal of power at once, on a small footprint. SEGRO's first fully fitted data centre in London's Park Royal has a 70 MVA incoming connection — at 5–10 MVA per large automated warehouse, that equals the consumption of 7–14 such facilities, on far less land.
The sum becomes decisive once land supply is considered. SEGRO holds more than 2.5 GW of powered land. Consuming 1.4 GVA through warehouses alone would take one or two hundred large automated facilities — no property owner holds that much land. Which is why SEGRO's half-year report of July 2026 set out two options side by side: industrial logistics projects on its land bank represent £313M of potential rent, while data centres drawing on 1.4 GVA represent £464M.
A warehouse pays more per megawatt but cannot consume all the available capacity. A data centre can. That, as the Tmtpost analysis concludes, is the fundamental difference between these two asset classes in the face of the European grid.
Is it working already?
Yes — this describes the current state of the market, not a forecast. Connection queues, non-firm capacity contracts and battery deployments are operating today. Confirmed figures: 15,498 entities on the Dutch waiting list by mid-2026, the date slippage in the Diemen sub-grid, and the availability of non-firm capacity contracts since January 2024.
The acquisition that completes this picture is in progress. Prologis bid for SEGRO in June 2026, SEGRO's board initially rejected it, and in August accepted a stock-and-cash option worth about £14B. The transaction — run as a formal takeover offer under the UK City Code on Takeovers and Mergers — is expected to close in the first half of 2027. The final price represented a 14 percent premium to adjusted net asset value per share and 39 percent to the share price the day before the offer.
What is not known: data from the CBRE, Savills and Knight Frank surveys are given as cited by Tmtpost — the full reports were not available for direct verification. Projections for 2027 remain projections.
Why does this matter?
Warehouse automation is ceasing to be a question of buying robots and becoming a question of access to power. The electricity grid is turning into a shared bottleneck for two entirely different industries, and queue position is settled at the level of regulation rather than technology. For warehouse owners that means a new competency — managing energy alongside leasing space.
What next?
- Prologis's acquisition of SEGRO is expected to close in the first half of 2027 — reshaping ownership of the UK's largest powered land bank
- Prologis forecasts that power constraints and planning barriers will push European logistics vacancy below 5 percent in 2026
- Identified regulatory risk: thresholds under the Energy Performance of Buildings Directive will cover the worst 16 percent of non-residential floor area by 2030 and 26 percent by 2033, while modernisation raises consumption per square metre